top of page

Depave 

In August 2009 we depaved 12 parking spaces, totaling 4500 square feet of asphalt, to create new garden space. This was done under the sponsorship of City Repair’s depave.org. This space has subsequently been turned into a 3,200 sq ft circular garden for annual food crops, with perimeter areas reserved for rain gardens, wildlife habitat, berry and grape production, space for cucurbit gardens, space for a neighborhood interface with bulletin board and seating for tea, and a courtyard for the community room.

Depave 2009 Schematic.png

The depave areas were marked, following the schematic, then cut into asphalt “tiles” one week before the big event. 8 dumpsters were rented to contain all the asphalt that was anticipated to be removed.

The day of the big event volunteers showed up bright and early. We had great weather.

After warm ups and a group photo, participants launched into the parking lot demolition with gusto. Starting from the north end, we moved our way south, loading up dumpster after dumpster.

Enthusiastic Depave Volunteers
Enthusiastic Depave Volunteers

We also removed a fair amount of “urbanite” and eventually a pickup load more of asphalt from all the perimeter areas.

Under a parking lot we discovered an old house foundation which created a lot more work to excavate and remove the foundation.

Our eventual goal is to depave most of the remaining car parking, reserving space only for community vehicles, bikes, and vehicle access to the building entrance for deliveries!

Besides the parking lot, we depaved a small area just outside unit 1 and a narrow strip along the south parking lot fence. The latter would allow us to grow a strip of vegetation that could climb the fence and really green this section of pavement. (It is now planted in bluebells and grape vines.)

Depave outside unit 1 completed.jpg
Depaving Outside Unit 1
Cutting Asphalt
Cutting Asphalt

  In late Spring we cut the asphalt into 3’x3′ tiles to prepare for a weekend blitz to remove the asphalt.

Several days later the big day for our community asphalt removing work party arrived. It was very hot but we had a tent set up to shade participants and plenty of snacks. Asphalt removal was more difficult than anticipated when we discovered it was extra thick and the cuts did not go all the way through in some areas. Nevertheless, with a great community effort, all the asphalt was removed by the end of the day. We removed a total of 4 dumpsters of asphalt chunks!

In Spring 2015 final plans were developed to depave the area outside units 1 through 4, a total of three and a half additional parking spaces. This area had served as our container garden for several years as plans evolved to transform this space into a permanent garden.

Removing the Middle Asphalt
Removing the Middle Asphalt

  A second work party was organized in the Fall to remove the gravel and prepare a winter cover crop. Removing the asphalt, we discovered what appeared to be a gravel filled trench running along the sidewalk and a large amount of gravel in the center. That graveled center area seemed perfect for a patio. We did not think too much about the trench and just covered it with plenty of compost.

  After the final perimeter gravel removal, we placed a large amount of compost on the area and then seeded it with daikon radish, chosen for its deep tap root’s ability to penetrate the heavy, very compacted, clay soil.

Scematic of Depave 2015.png

  One final surprise awaited us a few days later on Halloween day as residents were preparing holiday decorations for an evening party in the basement community room, below the depave site. There was a sudden and sustained downpour and all of a sudden, water started pouring into the room from the adjacent basement crawl space. Apparently the heavy downpour saturated the depave site and overflowed into the gravel trench, making its way into the basement crawl space next to the community room. Fortunately the flooding was intercepted by residents before it did any damage. We installed a sump pump in the area as the water flow into the crawl space continued intermittently for the duration of the Winter and Spring rains.

  By the next year, we were not sure if the basement leak had completely resolved since there was no problem with gentle rains and downpours are very infrequent. We had had no further flooding into the community room. We suspected the problem was due to a gravel filled trench in the depaved area that contained utility lines. The compacted soil on both sides was relatively impermeable compared to gravel, so rainwater would run into the trench and immediately proceed to the basement crawl space.

  The final step in the depave process was planting perennial natives as well as annuals and some vegetables.    One of the nicest features of this area is a large hollow stump out of which flows the entire rain water collected from the south half of the roof area. Even during a gentle rain this area now comes alive with a babbling brook and crosses under the bridges.

  Eventually, we decided to cap the trench area with a heavy clay layer to minimize risk of any further water entering the trench and making its way into the basement. This appears to have solved the problem, as well as continued cultivation of the formally compacted area, which is now more absorbent of water.

We have had no further problems, even during the heaviest downpours.

Depave 2015 Summer 2017
Summer 2017
More Photos

More Photos

2009

2015

bottom of page